Kindergarten Construction Technology-- demolition work process
2019-08-031661 Views
demolish remove is renovation Project the 1 stage work order ,According to drawing DesignRequirement, sure fixed need demolish remove Wall body , and sure fixed should Wall body is whether as bear heavy structure structure ,AndMain match electric box and Water table Location and walk towards ,Wall within Have no manage way line road Etc., sure fixed demolish remove back garbage pile place Site Etc.。 meanwhile do good implement work in Safety exchange connect work work , demolish remove front should about close HaveWater electric , work people wear wear Safety cap , do good Safety measure implement 。 demolish remove should from on towards under , from non bear heavy to bear heavy department position , demolish remove back garbage should and hour install bag transport to point fixed garbage pile place place 。