Kindergarten Light Steel Keel Gypsum Board Partition
2019-10-092601 Views
1. work art flow process
light steel keel separate Wall implement work flow process 1 time such as under : light separate Wall place line installation Door hole mouth frame ; installation along top keel and along keel ; vertical towards keel minutes file ; installation vertical towards keel ; installation horizontal towards keel card file ; installation gypsum cover surface board ; implement work connect seam do law ; surface floor implement work
2. place line :According toDesign implement work picture , in already do good surface or pillow bring on , place exit separate WallLocation line 、Door window hole mouth side frame line , and place good top keel Location side line 。
3. installation Door hole mouth frame : place line back according to Design, first Will separate WallDoor hole mouth frame installation complete graduate 。
4. installation along top keel and along keel : according to already place good separate WallLocation line , according to line installation top keel and keel , use radiation nail solid fixed at main body on , its radiation nail nail distance as 600mm。
5. vertical keel minutes file : According to separate Wall place line Door hole mouth Location, in installation top keel back , according to cover surface board rule grid 900mm or 1200mm board wide , minutes file rule grid dimension as 450mm, not enough model number minutes file should avoid open Door hole frame side the 1 block cover board Location, make break side gypsum cover surface board not in rely hole frame place 。
6. installation keel : according to minutes file Location installation vertical keel , vertical keel on under two end insert enter along top keel and along keel , adjust whole hang straight and Positioning standard sure back , use draw heart rivet nail solid fixed ; rely Wall、 pillar side keel use radiation nail or wood screw thread AndWall、 pillar solid fixed , nail distance as 1000mm。
7. installation horizontal towards card block keel :According toKindergartenDesignRequirement, separate WallHeight large at 3m hour should add horizontal towards card file keel , adopt towards draw heart rivet nail or screw bolt solid fixed 。
8. installation gypsum cover surface board
① inspection keel installation quality quantity 、Door hole mouth frame is whether comply with Design and structure build Requirement, keel room distance is whether comply with gypsum board Width model number 。
② installation 1 side paper surface gypsum board , from Door mouth place open begin , no Door hole mouth Wall body by Wall1 end open begin , gypsum board 1 general use self attack screw nail solid fixed , board side nail distance as 200mm, board in room distance as 300mm, screw nail distance gypsum board side edge Distance not small at 10mm, also not large at 16mm, self attack screw nail solid fixed hour , paper surface gypsum board must must And keel tight rely 。
③ installation Wall body within electric manage 、 electric box and electric box Equipment。
④ installation Wall body within Fireproofing、 separate voice 、 prevent moisture fill full Material,And another 1 side paper surface gypsum board meanwhile enter conduct installation fill enter 。
⑤ installation Wall body another 1 side paper surface gypsum board : installation Method same the 1 side paper surface gypsum board , its connect seam should And the 1 side surface board wrong open 。
⑥ installation double floor paper surface gypsum board : the 2 floor board solid fixed MethodAnd the 1 floor related same , but the 3 floor board connect seam should And the 1 floor wrong open , not can And the 1 floor connect seam fall in same 1 keel on 。
9. connect seam do law : paper surface gypsum board connect seam do law Have3 type form , immediately flat seam 、 concave seam and pressure strip seam 。 can according to with under process order place reason 。
① scrape embed seam putty child : scrape embed seam putty child front first Will connect seam within float soil clear remove dry clean , use small scrape knife putty child embed enter board seam ,And board surface fill real scrape flat 。
② adhesive paste pull structure bring : wait embed seam putty child condense solid original shape immediately conduct adhesive paste pull connect Material, first in connect seam on thin scrape 1 floor thick degree relatively sparse glue status putty child , thick degree as 1mm,Width as pull structure bring wide , follow immediately adhesive paste connect structure bring , use in scrape knife from on under OneDirection scrape flat pressure real , catch exit glue putty child And connect structure bring room air foam 。
③ scrape in floor putty child : pull structure bring adhesive paste back , establish immediately in on surface again scrape 1 floor than pull structure bring wide 80mm left right thick degree about 1mm in floor putty child , make pull structure bring bury enter this floor putty child in 。
④ find flat putty child : use large scrape knife Will putty child fill full wedge shape groove And board wipe flat 。
10.WallDecoration、 paper surface gypsum board Wall,According toDesignRequirement, can do Various decorate surface 。
(5) become product protect protect
1. light steel keel separate Wall implement work in , work type room should protect certificate already install Project not receive damage bad ,Wall within electric manage and Equipment not touch move wrong position and damage injury 。
2. light steel bone frame and paper surface gypsum board enter venue , exist place Use process in should proper kind protect manage , protect certificate not change shape , not receive moisture not dirty dye 、 no damage bad 。
3. implement work department position already installation Door window 、 surface 、Wall、 window platform Etc. should note meaning protect protect 、 prevent damage bad 。
4. already installation complete Wall body not touch hit , protect hold Wall not receive damage bad and dirty dye 。